Foundry
Baghouse Replaced in Two
Weeks, Filter Area Increased
88% While Staying in Same
Footprint at Indianapolis
Casting Facility
With its Indianapolis
diesel engine plant running
at full capacity for more
than two years, one of
the nation's largets automotive
suppliers demanded matching
speed from Kirk & Blum
in replacing a 20-year-old
foundry baghouse at its
Indianapolis casting facility.
The facility casts blocks
and heads for the engine
plant, adjacent to it on
the Indianapolis site,
as well as for other customers.
The old dust collector
at the foundry had to be
torn out and the new baghouse
installed, including all
new controls, over a two-week
vacation shutdown. "We
shut down 6 a.m. Saturday,
July 1 and needed to be
back up and running by
midnight, July 16," said
the manager of facilities
engineering at the plant.
The time squeeze was compounded
by one of space. Additional
baghouse capacity was needed,
but was restricted by other
structures at the site
to staying within the same
footprint.
Kirk & Blum
answered with:
Creative bag packaging,
redesigning the collectors
with tube sheets on staggered
centers to enable fitting
of more bags into the same
area.
Precision pre-fab and
modularization of major
components creating eight "packages" in
the shop, the largest that
could be trucked, then
joining them on-site into
just four units for lifting
into place by crane.
Tear-out took half the
time scheduled, all major
rigging work was completed
by the end of the first
week, and the new baghouse
was on-line, ready to go,
at the end of shutdown.
The new baghouse increases
cloth filter area by 88%,
is structurally stronger,
improves operator control
and automation, and provides
greater maintenance accessibility.
High
Pressure Project
Founded in 1907, Kirk & Blum
specializes in engineering,
fabrication, installation
and repair of dust and
fume control systems, and
all types of process ventilation
systems. It has extensive
experience with automotive
plants and the foundry
industry. Six Kirk & Blum
facilities in the midwest
and southeast U.S. enable
fast response and close
coordination on projects.
K&B's Indianapolis
plant performs many projects
for the large automotive
supplier, with major repairs
and up-grades scheduled
during summer shutdown. "However,
the baghouse replacement
eclipsed any previous shutdown
project in magnitude and
scope," stressed Tim
Schneider, Kirk & Blum
Vice President and head
of the Indianapolis facility. "This
was a high profile, high
pressure job. Without the
baghouse being in operation,
the foundry can't run the
molding line." Any
delay on start-up of the
foundry mold line could
have had a domino effect,
delaying production on
engines, then on all vehicles
to receive the engines.
"We had to compress
what would typically be
a six-week installation
project for a greenfield
site into two weeks with
no margin for delays or
fixes," said Mike
Richardson, K&B Project
Manager. "It was a
race against the clock.
Everything had to be done
on time and done right."
Creative
Packaging
Prevented by other plant
structures from building
outward to expand baghouse
capacity, Kirk & Blum
looked inward and upward.
Designed the collectors
with tube sheets having
staggered centers to enable
fitting more bags into
each bag compartment. Plus:
Increased bag length from
7-1/2 ft. to 10 ft.
Increased module size
by unitizing three compartments
with common wall sections,
so all available space
was utilized.
The new baghouse has 12
compartments, each with
248 bags. Bags are 6-1/4" diameter
x 10 ft long. The creative
packaging enables a total
of 48,695 sq. ft. of cloth
compared to 25,918 sq.
ft. previously. At the
existing system volume
of 174,000 CFM, the air-to-cloth
ration has been reduced
from 6.7:1 to 3.6:1.
"We needed more cloth
capacity," according
to the client's facilities
engineering department, "The
bags tended to load up
and bind, so they couldn't
clean properly. System
efficiency and air flow
were compromised." Decreasing
the air-to-cloth ratio
eliminated the load-up
problem. There is less
pressure drop, so the baghouse
draws more air without
increasing fan speed.
Easy
to Run and Maintain
Before the replacement,
capacity demands and system
design required that the
full baghouse be constantly
on-line, limiting maintenance
attention mostly to shutdowns.
Consequently, ease of maintenance
was given the highest priority
in all design consideration. "The
bag house redesign now
allows any of the 12 bag
compartments to be isolated
and taken off line at any
time for maintenance," the
client notes. "The
up-grade provides capacity
reserve, so there is no
problem in taking one of
the units off line."
Each compartment is fitted
with its own inlet and
automatic outlet dampers,
plus access door, enabling
isolation for maintenance
or cleaning. Each compartment
is fitted with a compressed
air header and 16 pulse
valves for automatic cleaning
cycles.
The baghouse redesign
greatly improved space
utilization and accessibility.
K&B enclosed the entire
baghouse complex, complete
with doors at each end
and each compartment, allowing
maintenance access to all
levels, including the roof.
Retractable stairs enable
access to the clean air
plenums. The enclosure
now provides space for
inside storage of replacement
baghouse components. New
lighting assures good visibility
and work lighting in enclosed
areas.
70's
to 90's Controls
Controls were totally
replaced. "We pretty
much went from 70's to
90's technology," said
the client. "It gives
us more options, more precise
control."
The installation included
two new Motor Control Centers
(MCC). These house all
of the motor starters,
transformers, controls,
programmable logic controller
(PLC), and the operator
interface. A new distribution
panel with circuit breakers
provides all control power.
The operator interface/computer
gives ICC an automated
system with more flexibility
and control of the baghouse
operation. The operator
interface displays the
baghouse operations on
graphics screens which
show the status of the
equipment, such as the
amperage of the four 150
hp fan motors, pressure
differentials, and damper
positions. This information
is constantly updated and
shown on the screens.
The operator interface
is connected to the PLC
which is used to send signals
to the control devices
in the system. The PLC
also receives signals from
remote mounted devices
which give indications
about the system operation.
The PLC uses this information
to initiate programmed
operations (such as start
a cleaning cycle) or sound
an alarm if there is a
problem. The PLC program
can be easily revised to
accommodate parameter changes
and additional equipment
that may be installed in
the future.
Precision
Pre-Fab
""The key for
Kirk & Blum in successfully
completing the field work
in the two-week time frame
was doing as much fabrication
and assembly as possible
ahead of time," stressed
Doug Harris, Field Superintendent.
K&B divided the structure
into eight sections, each
as big as could be transported
to the site by truck. Three
baghouse compartments were
utilized as single components
with common walls, consolidating
the 12 baghouse compartments
into four units. A matching
clean air plenum was created
for each 3-compartment
baghouse unit. On site,
each baghouse unit was
joined with its clean air
plenum. This left four
main "picks" by
a crane about 32,000 lbs.
each to erect the entire
baghouse complex. A 125-ton
crane was utilized for
the lifts.
"Fabrication of the
modules required custom-fitting," said
Harris. The rebuild retained
existing hoppers, on which
the new modules were mounted.
Structural steel supports
had to be reinforced to
accept the additional loads.
Existing manifolds were
also retained. These were
removed during tear-out,
then reinstalled with an
additional spool piece. "So,
everything had to be field
measured and fabricated
very accurately to fit
the existing structure," he
noted.
"The client had specified
10 gauge steel for a baghouse
with a 3/26" thick
tubesheet, which we upgraded
to 3/16" and 1/4" plate
respectively," said
Harris. "Our special
expertise and facilities
for plate work let us provide
the heavier construction
and real dollar value with
little increase in initial
costs."
"Well
Planned and Executed",
Said the Client
"K&B received
the full go-ahead from
the clienton the project
Apr. 1, only three months
from the start of shutdown.
Preliminary engineering
and field measurements
had been completed in order
to make a bid proposal
but the schedule still
left only 10 weeks to do
the shop fabrication," noted
Mike Richardson, K&B
project manager. "The
shop worked two shifts
the whole time to complete
the modules on schedule."
The fabrication phase
reinforced the client's
confidence that it had
made the right decision. "The
fab work settled any concerns
we may have had about being
able to complete the project
on schedule," said
the client. "Everything
was extremely well planned
and executed. You could
see it coming together
like clockwork."
Actually, Doug Harris,
K&B field superintendent,
admits to one mistake in
planning he allowed three
days for tear-out of the
old system, which actually
took only a day-and-a-half.
The savings proved crucial,
as late on the final week
before shutdown, as the
customer needed additional
production and decided
to run an extra day.
Field
Phase
Kirk & Blum put together
an installation team "second
to none" for the field
phase of the project, according
to Mike Richardson, K&B
project manager.
K&B used a 12-man
rigging crew for each shift
and worked two 10 hour
shifts for the first 11
days of the shutdown. Among
other things, they did
more than 3/4 of a mile
of field welding in less
than a week.
K&B's electrical subcontractor,
had a crew of 7 or 8 people
per shift during the second
week of installation. They
completed all required
tearout, installation and
testing of the new control
system.
A crew of five pipefitters
installed the compressed
air piping used to clean
the filter bags.
An insulating crew was
hired to spray polyurethane
insulation on the interior
of the baghouse to prevent
condensation. The main
internal sections of bag
compartments, clean air
and dirty air plenums were
insulated before being
lifted into position. Later,
after the units had been
welded together, the foam
crew returned to insulate
the seams. When the insulating
work was completed, a separate
crew applied fire retardant
material to the entire
baghouse interior.
Two cranes and operators
handled lift requirements
a 125 ton unit for the
main picks, while a smaller
crane lifted roofing, interior
floors and smaller, miscellaneous
components and equipment.
"We had a lot of
people crawling around
in a small, confined area," said
Richardson. "Our biggest
problem was staying out
of each other's way."
Team
Project
"This was a great
team effort," stressed
Schneider, K&B VP in
charge of the Indianapolis
plant. "The guys in
the field really came through
with the pressure on and
the clock ticking. but,
they needed the guys in
the shop to do their job
right. When everything
fits it makes things so
much easier in the field."
Did he ever have doubts
about finishing the baghouse
job on schedule? "I
better not have," said
Schneider. "We scheduled
the crew to go straight
to another two-week shutdown
project at another foundry." |